Contract 202056022 E. 16th Avenue System, Phase 1

General Statement of Work

The East 16th Avenue Storm Sewer Improvements, Phase 1 project is the first phase of an effort to extend and upsize the storm system in the Montclair Basin to relieve frequent and significant flooding in the neighborhood. The downstream end of the project will tie into an existing box in Jackson Street at East 17th Avenue that outfalls into Ferril Lake. The new storm drain will extend via a 9'x9' box east in East 17th Avenue to Colorado Boulevard. Tunneling will be required to cross under Colorado Boulevard. Work will also include a trash vault, full roadway reconstruction, full utility reconstruction, and improvements to the existing system on Batavia Place between Colorado Boulevard and Albion Street. Two alternates to the bid will continue the system east from Colorado Boulevard along East 17th Avenue to Albion Street and then south on Albion Street to Batavia Place.

Estimated Construction Cost

Between $8,500,000.00 and $9,400,000.00

Statement of Quantities (PDF)

Pre-bid Meeting on October 8, 2020 at 9:00 a.m.

To access the meeting, please call 720-388-6219 and enter the conference ID: 604 038 932#.

Meeting Agenda (PDF)

Sign-in Sheet (PDF)

Questions Deadline Extended To:

December 3, 2020 at 10:00 a.m. local time

NEW BID OPENING DATE!

Bid Opening on December 17, 2020 at 11:00 a.m.

Bids will be received and accepted via the online electronic bid service, www.QuestCDN.com. To access the meeting, please call 720-388-6219 and enter the conference ID: 604 038 932#.

Plans Available September 30, 2020

Digital Download

QuestCDN Project #7318743

Plan Cost  $15.00

MWBE goal: 15%

Prequalification

1E(4) Piped Sewer at or above the $9,000,000.00 monetary level.

Contract Administrator

Isabelle Oldani

pw.procurement@denvergov.org 

Prevailing Wage and Minimum Wage:  Contracts for construction, reconstruction, and remodeling are subject to the City prevailing wage rate requirements established pursuant to Section 20-76, D.R.M.C.  City contracts are subject to payment of City Minimum Wage established pursuant to Section 20-82 through 20-84 D.R.M.C.

As the City’s best interests may appear, the Executive Director of the Department of Transportation and Infrastructure reserves the right to waive informalities in, and to reject any or all, submittals.

FOR COMPLETE DESCRIPTION SEE AD IN The Daily Journal ON THE FOLLOWING DATES:

Wednesday, September 30, October 1, 2, 2020